Roadway, Water, and Construction Projects
===========================================================
ROADWAY PROJECTS
WEST LUCAS ROAD WIDENING
Update – May 25, 2021
Status – Planning
Designer – TBD
Contractor – TBD
2019 Budget – $12,550,000
Design Cost – TBD
Construction Cost – TBD
From – Angel Parkway
To – Country Club Road
Schedule:
June 2021 - Survey Information Complete; Typical Section Verification; and Pavement Design
September 2021 - 60% Plans to City and Country
October 2021 - Second Neighborhood Meeting and Preliminary Plans to Utilities
November 2021 - 90% Plans to City and Country
March 2022 - Final Plans and Bid Documents
June 2022 - Construction Starts
2024 - Construction Ends
West Lucas Road Proposed Improvements
WATERWORKS PROJECTS
BAIT SHOP INTERSECTION WATERLINE RELOCATIONS
Update – May 25, 2021
Status – Design
Designer – Huitt-Zollors
Location – Lucas Road/Southview Drive Intersection
2020 Budget Estimate – $500,000
Design and Construction Cost – $500,000 Revised to $800,000
Schedule:
February 2021 – Design Starts
April 2021 - Preliminary Design
Late April 2021 - City Review
May 2021 - Pre‐Final Design Completed
May & June 2021 - City and TxDOT Review
June 2021 - Final Plans Signed/Sealed
July/August 2021 - Construction Starts
TBD - Construction Ends
As part of the TxDOT FM 1378/FM 3286 (aka Bait Shop) Intersection project, the City of Lucas will need to relocate 3,000+/- linear feet of 12-inch waterlines: Section A) 1,900 LF from Edgefield Lane to Prado Verde Drive along W. Lucas Road and Southview Drive and Section B) 1,100 LF from Southview Drive to Lost Valley Drive along E. Lucas Road.
TEXAS DEPARTMENT OF TRANSPORTATION (TxDOT) PROJECTS
TxDOT - Bait Shop (FM 1378/FM 3286) Intersection
Update – January 7, 2021
Status – Design
Budget – $4,000,000 to $5,000,000
CSJ: 1392-01-044
Schedule (Per City Staff)
2018-2020 -- Environmental Work
2020-2021 -- Design Work
May 2023 -- Construction Starts
2025 -- Construction Ends
Some folks in Lucas refer to this intersection (Lucas Road/Southview Drive) as the intersection by the Bait Shop.
Draft Bait Shop Schematic Plans August 2020
TxDOT - Angel Parkway (FM 2551)
From Estates Parkway
To Parker Road
Update – January 7, 2021
Status – Design
Budget – $11.5 Million
CSJ: 2056-01-042
July 2022 -- Construction Starts
Reconstruct and widen from two lane to six lane divided
TxDOT - FM 1378 (Country Club Road, W. Lucas Road, and Southview Drive)
From - Stacy Road
To - Parker Road
CSJ: 1392-01-047
Status - Feasibility Study
TxDOT - W. Lucas Road (FM 1378)
From - Country Club Road
To - Southview Drive
CSJ: 1392-01-048
Status - NEPA Feasibility Study
TxDOT - Estates Parkway (FM 2170) Safety Enhancements
From - Angel Parkway
To - Country Club Road
CSJ: 1392-01-048
Status - Design
Schedule:
Construction Starts
Construction Ends