Roadway, Water, and Construction Projects

Winningkoff Road Phase 2 Traffic

This week Winningkoff will remain open to one-way northbound, one-lane traffic. Staff is working with the contractor to place the final traffic control switch in place next week. This final switch will close Winningkoff to all through traffic north of 1090 Winningkoff and south of Manor Lane. Access to the three driveways south of Manor Lane will be maintained via a one-lane, two-way road, and all access north of Manor Lane (including Manor Lane) will be maintained via a two-way, two-lane Winningkoff Road. Access to 1090 Winningkoff will be maintained from the Winningkoff/Forestview intersection via a two-lane, two-way Winningkoff. There will be short areas of one-lane traffic throughout the project based on pavement placement/pours. This final switch should remain in place for 60 days.

===========================================================

ROADWAY PROJECTS

WINNINGKOFF ROAD PHASE 2

Update – January 7, 2021
Status – Construction
Designer – Birkhoff, Hendricks & Carter
Contractor – Camino Construction, LP
2016 Budget – $1,400,000
Design Cost – $215,850
Construction Cost – $1,843,474
Construction Contingency – $184,347
Project Management Cost – $139,890
2020 Project Cost – $2,167,711**

From – Reverse Curve
To – Snider Lane
Schedule:
June 2018 – Design Complete
July 2018 revised to April 2019 – Plans ready for Advertising, Bidding, and Awarding
Fall 2018 revised to February 2021 – Construction Starts
Late 2023 revised to October 2021 – Construction Ends

Winningkoff Road Construction/Engineering Plans
Winningkoff Road Change Order #01*

* Change Order #01 used $16,613.62 of the $184,347 in Construction Contingency.
** A Project Management contract was added to the project to accelerate the schedule and improve inspection.  A 10% Construction Contingency was added to the project to fund unforeseen construction challenges.  The original contractor was replace with next lowest A+B bidder:  Camino Construction.

WEST LUCAS ROAD WIDENING

Update – May 25, 2021
Status – Planning
Designer – TBD
Contractor – TBD
2019 Budget – $12,550,000
Design Cost – TBD
Construction Cost – TBD

From – Angel Parkway
To – Country Club Road

Schedule:
June 2021 - Survey Information Complete; Typical Section Verification; and Pavement Design
September 2021 - 60% Plans to City and Country
October 2021 - Second Neighborhood Meeting and Preliminary Plans to Utilities
November 2021 - 90% Plans to City and Country
March 2022 - Final Plans and Bid Documents
June 2022 - Construction Starts
2024 - Construction Ends

West Lucas Road Proposed Improvements 

WATERWORKS PROJECTS

THIRD WATER TOWER (f.k.a. NORTH PUMP STATION WATER TOWER)

Update – May 25, 2021
Status – Planning
Designer – TBD
Location – TBD
2019 Budget -- $2,000,000
Design Cost – TBD.

Water Tower Schedule:  TBD

BAIT SHOP INTERSECTION WATERLINE RELOCATIONS

Update – May 25, 2021
Status – Design
Designer – Huitt-Zollors
Location – Lucas Road/Southview Drive Intersection
2020 Budget Estimate – $500,000
Design and Construction Cost – $500,000 Revised to $800,000

Schedule:
February 2021 – Design Starts
April 2021 - Preliminary Design
Late April 2021 - City Review
May 2021 - Pre‐Final Design Completed
May & June 2021 - City and TxDOT Review
June 2021 - Final Plans Signed/Sealed
July/August 2021 - Construction Starts
TBD - Construction Ends

As part of the TxDOT FM 1378/FM 3286 (aka Bait Shop) Intersection project, the City of Lucas will need to relocate 3,000+/- linear feet of 12-inch waterlines:  Section A) 1,900 LF from Edgefield Lane to Prado Verde Drive along W. Lucas Road and Southview Drive and Section B) 1,100 LF from Southview Drive to Lost Valley Drive along E. Lucas Road.

 

TEXAS DEPARTMENT OF TRANSPORTATION (TxDOT) PROJECTS

TxDOT - Bait Shop (FM 1378/FM 3286) Intersection

Update – January 7, 2021
Status – Design
Budget – $4,000,000 to $5,000,000
CSJ: 1392-01-044
Schedule (Per City Staff)
2018-2020 -- Environmental Work
2020-2021 -- Design Work
May 2023 -- Construction Starts
2025 -- Construction Ends

Some folks in Lucas refer to this intersection (Lucas Road/Southview Drive) as the intersection by the Bait Shop.

Draft Bait Shop Schematic Plans August 2020

TxDOT - Angel Parkway (FM 2551)

From  Estates Parkway
To Parker Road
Update – January 7, 2021
Status – Design
Budget – $11.5 Million
CSJ:   2056-01-042
July  2022 -- Construction Starts
Reconstruct and widen  from two  lane to six lane divided

Partial Plan Set

TxDOT - FM 1378 (Country Club Road, W. Lucas Road, and Southview Drive)

From - Stacy Road
To - Parker Road
CSJ:  1392-01-047
Status - Feasibility Study

TxDOT - W. Lucas Road (FM 1378)

From - Country Club Road
To - Southview Drive
CSJ:  1392-01-048
Status - NEPA Feasibility Study

TxDOT - Estates Parkway (FM 2170) Safety Enhancements

From - Angel Parkway
To - Country Club Road
CSJ:  1392-01-048
Status - Design

Schedule:
Construction Starts
Construction Ends

 

Close window