Roadway, Water, and Construction Projects
===========================================================
ROADWAY PROJECTS
BLONDY JHUNE ROAD REALIGNMENT AT COUNTRY CLUB
Update - October 17, 2022
Status - In Construction
Designer - Kimley Horn
Contractor - Precision Concrete and Excavation
From - Blondy Jhune Rd First Curve
To - Country Club Road
Schedule
Detour Route and Traffic Control Plan
WEST LUCAS ROAD WIDENING
Update – September 26, 2022
Status – Design
Designer – BCC Engineering
Contractor – TBD
2019 Budget – $12,550,000
Design Cost – TBD
Construction Cost – TBD
From – Angel Parkway
To – Country Club Road
West Lucas Road Proposed Improvements
WATERWORKS PROJECTS
BAIT SHOP INTERSECTION WATERLINE RELOCATIONS
Update – September 26, 2022
Status – Pre-Bid
Designer – Huitt-Zollors
Location – Lucas Road/Southview Drive Intersection
2020 Budget Estimate – $500,000
Design and Construction Cost – $500,000 Revised to $800,000
As part of the TxDOT FM 1378/FM 3286 (aka Bait Shop) Intersection project, the City of Lucas will need to relocate 3,000+/- linear feet of 12-inch waterlines: Section A) 1,900 LF from Edgefield Lane to Prado Verde Drive along W. Lucas Road and Southview Drive and Section B) 1,100 LF from Southview Drive to Lost Valley Drive along E. Lucas Road.
TEXAS DEPARTMENT OF TRANSPORTATION (TxDOT) PROJECTS
TxDOT - Bait Shop (FM 1378/FM 3286) Intersection
Update – January 7, 2021
Status – Design
Budget – $4,000,000 to $5,000,000
CSJ: 1392-01-044
Schedule (Per City Staff)
2018-2020 – Environmental Work
2020-2021 – Design Work
May 2023 – Construction Starts
2025 – Construction Ends
Some folks in Lucas refer to this intersection (Lucas Road/Southview Drive) as the intersection by the Bait Shop.
TxDOT - Angel Parkway (FM 2551)
From Estates Parkway
To Parker Road
Update – January 7, 2021
Status – Utility Relocation
Budget – $11.5 Million
CSJ: 2056-01-042
July 2022 – Construction Starts
Reconstruct and widen from two lane to six lane divided
TxDOT - Estates Parkway (FM 2170) Safety Enhancements
From - Angel Parkway
To - Country Club Road
CSJ: 1392-01-048
Status - Pre-Construction
Schedule:
Construction Starts – January 2023
Construction Ends – September 2023