Roadway, Water, and Construction Projects

===========================================================

ROADWAY PROJECTS

WEST LUCAS ROAD WIDENING

Update – September 26, 2022
Status – Design
Designer – TBD
Contractor – TBD
2019 Budget – $12,550,000
Design Cost – TBD
Construction Cost – TBD

From – Angel Parkway
To – Country Club Road

West Lucas Road Proposed Improvements 

WATERWORKS PROJECTS

BAIT SHOP INTERSECTION WATERLINE RELOCATIONS

Update – September 26, 2022
Status – Pre-Bid
Designer – Huitt-Zollors
Location – Lucas Road/Southview Drive Intersection
2020 Budget Estimate – $500,000
Design and Construction Cost – $500,000 Revised to $800,000

As part of the TxDOT FM 1378/FM 3286 (aka Bait Shop) Intersection project, the City of Lucas will need to relocate 3,000+/- linear feet of 12-inch waterlines:  Section A) 1,900 LF from Edgefield Lane to Prado Verde Drive along W. Lucas Road and Southview Drive and Section B) 1,100 LF from Southview Drive to Lost Valley Drive along E. Lucas Road.

TEXAS DEPARTMENT OF TRANSPORTATION (TxDOT) PROJECTS

TxDOT - Bait Shop (FM 1378/FM 3286) Intersection

Update – January 7, 2021
Status – Design
Budget – $4,000,000 to $5,000,000
CSJ: 1392-01-044
Schedule (Per City Staff)
2018-2020 -- Environmental Work
2020-2021 -- Design Work
May 2023 -- Construction Starts
2025 -- Construction Ends

Some folks in Lucas refer to this intersection (Lucas Road/Southview Drive) as the intersection by the Bait Shop.

Draft Bait Shop Schematic Plans August 2020

TxDOT - Angel Parkway (FM 2551)

From  Estates Parkway
To Parker Road
Update – January 7, 2021
Status – Utility Relocation
Budget – $11.5 Million
CSJ:   2056-01-042
July  2022 -- Construction Starts
Reconstruct and widen  from two  lane to six lane divided

Partial Plan Set

TxDOT - Estates Parkway (FM 2170) Safety Enhancements

From - Angel Parkway
To - Country Club Road
CSJ:  1392-01-048
Status - Pre-Construction

Schedule:
Construction Starts
Construction Ends

 