Roadway, Water, and Construction Projects

Keep up to date on construction project information throughout the City by sending an email to [email protected] requesting to be added to the Construction Update email list.

Brockdale Park Road – TexasBit is planning to start this week. The roadway will be open to traffic during the construction, but motorists should expect delays.

SuddenLink Fiber – The City has issued a permit for the installation of underground and aerial SuddenLink fiber to the Rimrock, Claremont Springs, Travis Ranch, and Konrad Ranch neighborhoods. SuddenLink has not provided a schedule for when fiber will be available to these areas.

Brockdale Park Road – TexasBit is planning to start next week. The roadway will be open to traffic during the construction, but motorist should expect delays.

Winningkoff Road Phase 2 – The availability of concrete remains an issue for the contractor. Several scheduled concrete deliveries were cancelled during the past two weeks, which has impacted the overall schedule. The contractor is on schedule to open the road to northbound traffic on May 15.

West Lucas Road Neighborhood Meeting – Approximately ten citizens attended the neighborhood meeting to discuss the West Lucas Road project on May 4, 2021. The West Lucas Road project will reconstruct West Lucas Road from Angel Parkway to Country Club Road to a four-lane divided roadway. The proposed project schedule was discussed which included the following milestones:

Neighborhood Meeting                    May 4, 2021
Survey Information Complete            June 2021
Typical Section Verification                June 2021
Pavement Design                                June 2021
60% Plans to City and Country          September 2021
Neighborhood Meeting                      October 2021
Preliminary Plans to Utilities              October 2021
90% Plans to City and Country       November 2021
Final Plans and Bid Documents         March 2022
Construction is anticipated to begin in June 2022

===========================================================

ROADWAY PROJECTS

WINNINGKOFF ROAD PHASE 2

Update – January 7, 2021
Status – Construction
Designer – Birkhoff, Hendricks & Carter
Contractor – Camino Construction, LP
2016 Budget – $1,400,000
Design Cost – $215,850
Construction Cost – $1,843,474
Construction Contingency – $184,347
Project Management Cost – $139,890
2020 Project Cost – $2,167,711**

From – Reverse Curve
To – Snider Lane
Schedule:
June 2018 – Design Complete
July 2018 revised to April 2019 – Plans ready for Advertising, Bidding, and Awarding
Fall 2018 revised to February 2021 – Construction Starts
Late 2023 revised to October 2021 – Construction Ends

Winningkoff Road Construction/Engineering Plans
Winningkoff Road Change Order #01*

* Change Order #01 used $16,613.62 of the $184,347 in Construction Contingency.
** A Project Management contract was added to the project to accelerate the schedule and improve inspection.  A 10% Construction Contingency was added to the project to fund unforeseen construction challenges.  The original contractor was replace with next lowest A+B bidder:  Camino Construction.

WEST LUCAS ROAD WIDENING

Update – January 7, 2021
Status – Planning
Designer – TBD
Contractor – TBD
2019 Budget – $12,550,000
Design Cost – TBD
Construction Cost – TBD

From – Angel Parkway
To – Country Club Road
Schedule:
2021-2022 – Design
2022-2024 – Construction

 

WATERWORKS PROJECTS

NORTH PUMP STATION PUMP HOUSE

Update – January 7, 2021
Status – Construction
Designer – BW2 Engineers
Contractor -- Lamarc, Inc.
Location – 915 Country Club Road

Design Cost – $215,850
Construction Cost – $1,457,037
Construction Contingency – $145,730*
Project Management Cost – $69,945
2019 Project Cost – $1,672,712**

Schedule:
October 22, 2019 – Construction Started
May/June 2020 revised to February 2021 – Construction Ends

* Change Orders #01 used $44,543.90 and #02 used $16,556.28 of the $145,730 in Construction Contingency.
** A Project Management contract was added to the project to accelerate the schedule and improve inspection.  A 10% Construction Contingency was added to the project to fund unforeseen construction challenges.

NORTH PUMP STATION WATER TOWER

Update – January 7, 2021
Status – Planning
Designer – TBD
Location – TBD
2019 Budget -- $2,000,000
Design Cost – TBD.

Water Tower Schedule:  TBD

SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)

Update – October 2, 2020
Status – Design
Designer – BLOC Design-Build, LLC
Location – City Wide
2019 Budget – $100,000
Design and Construction Cost – $90,823
Schedule:
July 2019 revised to May 2020 – Design
– Plans ready for Advertising, Bidding, and Awarding
June 22, 2020 – Construction Started
September 2020 revised to February 2021 – Construction Ends.

BAIT SHOP INTERSECTION WATERLINE RELOCATIONS

Update – January 8, 2021
Status – Planning
Designer – TBD
Location – Lucas Road/Southview Drive Intersection
2020 Budget Estimate – $500,000
Design and Construction Cost – $500,000
Schedule:
February 2021 – Design Starts
TBD – Construction Starts
TBD – Construction Ends.

As part of the TxDOT FM 1378/FM 3286 (aka Bait Shop) Intersection project, the City of Lucas will need to relocate 3,000+/- linear feet of 12-inch waterlines:  Section A) 1,900 LF from Edgefield Lane to Prado Verde Drive along W. Lucas Road and Southview Drive and Section B) 1,100 LF from Southview Drive to Lost Valley Drive along E. Lucas Road.

 

TEXAS DEPARTMENT OF TRANSPORTATION (TxDOT) PROJECTS

TxDOT - Bait Shop (FM 1378/FM 3286) Intersection

Update – January 7, 2021
Status – Design
Budget – $4,000,000 to $5,000,000
CSJ: 1392-01-044
Schedule (Per City Staff)
2018-2020 -- Environmental Work
2020-2021 -- Design Work
May 2023 -- Construction Starts
2025 -- Construction Ends

Some folks in Lucas refer to this intersection (Lucas Road/Southview Drive) as the intersection by the Bait Shop.

Draft Bait Shop Schematic Plans August 2020

TxDOT - Angel Parkway (FM 2551)

From  Estates Parkway
To Parker Road
Update – January 7, 2021
Status – Design
Budget – $11.5 Million
CSJ:   2056-01-042
July  2022 -- Construction Starts
Reconstruct and widen  from two  lane to six lane divided

Partial Plan Set

TxDOT - FM 1378 (Country Club Road, W. Lucas Road, and Southview Drive)

From - Stacy Road
To - Parker Road
CSJ:  1392-01-047
Status - Feasibility Study

TxDOT - W. Lucas Road (FM 1378)

From - Country Club Road
To - Southview Drive
CSJ:  1392-01-048
Status - NEPA Feasibility Study

Close window